Ekon had signed the contract for Afşin Elbistan B Power Plant 2nd Unit Fire Damage Restoration Project on 16th January 2015 and effective date of this Contract was 13th February 2015.
The duration of this contract was 600 days of which contractual deadline was 5th October 2016. The project has successfully been completed ahead of the schedule with actual completion date of 23 September 2016 by the start of Trial Operation Period.
Performance tests have successfully been completed on 15-16th December 2016 and Provisional Acceptance Protocol has been mutually signed by EÜAŞ and EKON on 26th January 2017 without any punch list item. Provisional Acceptance Protocol has been approved by EÜAŞ on 4th April 2017.
.