EKON Industry Construction and Trade Inc. has been awarded the hydro mechanical equipment manufacturing and erection works for the Tepekışla Dam and Hydroelectric Power Plant Project in Erbaa Tokat by Ark Energy on the 6th January 2014.
The Project is located between Erbaa and Niksar, which is approximately 80 km north of the city of Tokat and approximately 200 km south of the city of Samsun on the Kelkit River. The hydroelectric power plant is composed of two big and one smaller units, with the total capacity of 68.5 MW.
The project will cover the manufacturing, erection, testing and commissioning works of mechanical and hydro mechanical equipment, and also supply and provision of the spare parts and its duration will be 11 months.
EKON Industry Construction and Trade Inc. shall perform engineering services, design, manufacturing, procurement, assembly, performance tests, shipping of mechanical and hydro mechanical equipment, structural steel spare parts of needed equipment’s and maintenance service during guarantee period.