projects Description
Project :

Vanazit Hydroelectric Power Plant Project Civil Works Of Water Intake Structure,Pipe Line, Forebay, Penstock Pipeline, Turbine Building, Power TransmissionsLine

Client : PROENEnerji ve Madencilik A.Ş.
Contract Date : 02.01.2012
Duration : 12 Months
Status : Main Contractor
Percentage Of Participation : 100 %
Detailed Description Of The Project : The Project area is located in Keşap district, which is in Giresun on the Büyük River in Black Sea region.The hydroelectric plant is composed of one unit, which has 3,50 m3/s maximum project inflow, 108,38 m gross head and 3,46 MW installed capacity.All civil works are within the scope of project.
Detailed Description Of The Project : Concrete : 18.000 m³

Reinforcement : 900 tons