Project | : |
Vanazit Hydroelectric Power Plant Project Civil Works Of Water Intake Structure,Pipe Line, Forebay, Penstock Pipeline, Turbine Building, Power TransmissionsLine |
Client | : | PROENEnerji ve Madencilik A.Ş. |
Contract Date | : | 02.01.2012 |
Duration | : | 12 Months |
Status | : | Main Contractor |
Percentage Of Participation | : | 100 % |
Detailed Description Of The Project | : | The Project area is located in Keşap district, which is in Giresun on the Büyük River in Black Sea region.The hydroelectric plant is composed of one unit, which has 3,50 m3/s maximum project inflow, 108,38 m gross head and 3,46 MW installed capacity.All civil works are within the scope of project. |
Detailed Description Of The Project | : | Concrete : 18.000 m³
Reinforcement : 900 tons Formwork : 25.000 m² |