Project | : |
2 x 610 MW Sugözü Thermal Power Plant Civil Works, Turkey |
Client | : | GAMA ‚ Tekfen Joint Venture |
Contract Date | : | 29.11.2000 |
Completion Date | : | The project has been completed on 30.09.2002. |
Duration | : | 2 Years |
Status | : | Sub-Contractor |
Percentage Of Participation | : | 100 % |
General Description Of The Project | : | The project has been formed of 3 separate contracts covering the Coal Park Area Construction, Switch Area Construction and Turbine Building Foundations Construction works. |
Liquidated Dameges | : | None |
projects Description
- 0
- 6 June 2022
- Energy & Power