Projeler - Kardemir Gas Cooling and Cleaning Plant

Projeler - Kardemir Gas Cooling and Cleaning Plant

projects Description
Project : Converter Gases Cooling and Cleaning Plant for KARDEMIR Karabük, Zonguldak – Turkey
Client : KARDEMİR Karabük Iron and Steel Factory Inc.
Contract Date : 01.12.1997
Completion Date : The project has been completed on 24.05.1999.
Duration : 18 Months
Status : Main Contractor
Percentage Of Participation : 100 %
General Description Of The Project :

The project had two stages:

  • First stage covered the Engineering, Procurement and Supply of Equipment.
  • The second stage covered the Civil Works, Erection Works and Commissioning ofthe Converter Gases Cooling and Cleaning Plant for KARDEMİR Karabük Iron andSteel Factory Inc.
Detailed Description Of The Project : Civil Works:

  • Excavation : 12,000 m3
  • Concrete : 3,900 m3
  • Formwork : 9,172 m2
  • Scaffolding : 15,000 m3
  • Reinforcement : 208 tons

Mechanical Works:

  • Design, Manufacturing, Supply and Erection of Technological Equipment : 600 tons
  • Design and Supply of Piping Works : 200 tons
  • Design and Erection Works of Automation System (PLC, MCC, MMI) : 450 nos.
  • Cable Supply & Erection : 77,000 m
  • Conduit Supply and Erection : 3,500 m
  • Lightening Works