Projeler - Kangal Thermal Power Plant (3×150 MW) ESP Rehabilitations

Projeler - Kangal Thermal Power Plant (3×150 MW) ESP Rehabilitations

projects Description
Project :

Kangal Thermal Power Plant Rehabilitions Of Electrostatic Precipitators And Ash

Handling System For Units 1 & 2, Kangal – Sivas

Client : EÜAŞ ‚Äì Electric Production Inc.
Contract Date : 12.10.2000
Completion Date : The project has been completed on 25.07.2003.
Status : Main Contractor
Percentage Of Participation : 100 %
General Description Of The Project : The Project covers the replacement of existing electrostatic precipitators with the new ones, installing a new gas analyzer, revamping of ash handling systems, erection and commissioning works.
Liquidated Dameges : None