| Project | : |
Kangal Thermal Power Plant Rehabilitions Of Electrostatic Precipitators And Ash Handling System For Units 1 & 2, Kangal – Sivas |
| Client | : | EÜAŞ ‚Äì Electric Production Inc. |
| Contract Date | : | 12.10.2000 |
| Completion Date | : | The project has been completed on 25.07.2003. |
| Status | : | Main Contractor |
| Percentage Of Participation | : | 100 % |
| General Description Of The Project | : | The Project covers the replacement of existing electrostatic precipitators with the new ones, installing a new gas analyzer, revamping of ash handling systems, erection and commissioning works. |
| Liquidated Dameges | : | None |