Project : İSDEMİR Modernization Investment Programme Ore Dressing Facility in İskenderun
Client : İSDEMİR ‚ İskenderun Iron & Steel Co.
Consultant : ERENCO ‚ Erdemir Engineering Management & Consulting Services Inc.
Contract Date
Commencement Date
:

:

05.03.2007

08.03.2007

Duration : 450 Day
Status : Main Contractor
Percentage Of Participation :

100 %

General Description Of The Project : Scope of the project includes modernization, engineering, production, construction and erection of ore preparation system, blending and manipulation of raw material.
Detailed Description Of The Project : Sections of Factory:

  • Conveyor : 500 m
  • Stacker : Erection
  • Reclaimer : Erection

Completed works:

  • Excavation : 000 m3
  • Piling : 000 m
  • Concrete : 000 m3
  • Steel Structure : 800 tons
  • Electrical System ( Complete )
  • Automation System
  • Instrumentation
Main Subcontractor : SIEMENS