Project | : |
Aşkale Cement Factory With Capacity 3500 ton on Bases Turn-Key Construction of New Klinker Line,Erzurum -Turkey |
Client | : | Aşkale Cement Industry Inc. |
Contract Date | : | 02.02.2006 |
Completion Date | : | Clinker production started at 29.07.2007. Provisional Acceptance Certificate has been issued on 20.08.2007. |
Duration | : | 20 Months |
Status | : | Main Contractor |
Percentage Of Participation | : | 100 % |
General Description Of The Project | : | The project covers the construction of cement plant with 3500 tons/day clinker capacity. |
Detailed Description Of The Project | : | The plant consists of :
|
Liquidated Damages | : | None |
Main Subcontractors | : | KHD HUMBOLT WEDAG, Germany GEBR PFEIFFER AG – Germany |