Project |
: |
Converter Gases Cooling and Cleaning Plant for KARDEMIR Karabük, Zonguldak – Turkey |
Client |
: |
KARDEMİR Karabük Iron and Steel Factory Inc. |
Contract Date |
: |
01.12.1997 |
Completion Date |
: |
The project has been completed on 24.05.1999. |
Duration |
: |
18 Months |
Status |
: |
Main Contractor |
Percentage Of Participation |
: |
100 % |
General Description Of The Project |
: |
The project had two stages:
- First stage covered the Engineering, Procurement and Supply of Equipment.
- The second stage covered the Civil Works, Erection Works and Commissioning ofthe Converter Gases Cooling and Cleaning Plant for KARDEMİR Karabük Iron andSteel Factory Inc.
|
Detailed Description Of The Project |
: |
Civil Works:
- Excavation : 12,000 m3
- Concrete : 3,900 m3
- Formwork : 9,172 m2
- Scaffolding : 15,000 m3
- Reinforcement : 208 tons
Mechanical Works:
- Design, Manufacturing, Supply and Erection of Technological Equipment : 600 tons
- Design and Supply of Piping Works : 200 tons
- Design and Erection Works of Automation System (PLC, MCC, MMI) : 450 nos.
- Cable Supply & Erection : 77,000 m
- Conduit Supply and Erection : 3,500 m
- Lightening Works
|